The walls are finished up to roof level, as you were told. But no roof timber is on site yet, so roofing can't start next week as planned. Worth asking before you send the roofing payment.
| What you were told (your message, 14 Nov) | What we saw on 17 Nov | Match | |
|---|---|---|---|
| Walls | "All walls are up to wall-plate (roof level)." | All four outside walls and inside walls are up to roof level. Window and door openings are in place, no frames yet. Photos P01–P10. | YES |
| Roof timber | "Roof timber has been bought and delivered." | No roof timber (trusses or rafters) anywhere on the plot. Short timber ends stick out of the wall top, but these are not roof timbers. P09, P11. | NO |
| Iron sheets | "Sheets delivered." | 12 new iron sheets stacked on timber offcuts near the gate. Whether 12 is the full order: we can't tell. P11. | PARTLY |
| Workers | "Team of 5 on site this week." | Nobody on site during our visit (10:12–10:58, a Tuesday). Gate was closed but not locked. | ASK |
| Next step | "Roofing starts next week. Please send KES 180,000 for roofing labour." | Roofing would first need the roof timber on site. | ASK |
| # | What we saw | Where | Level |
|---|---|---|---|
| 1 | No roof timber on site, although you were told it was delivered. | Whole plot · P09, P11 | Needs attention |
| 2 | A crack about 40 cm long down the side of the water-tank stand, running from the top edge. | Back of house · P05 | Needs attention |
| 3 | Blue tarpaulin over the front wall top is loose at one end; rain can reach the wall top. | Front wall · P01 | Minor |
| 4 | Water meter: not found at the gate or boundary. | Boundary | Not seen |
Taken in-app on Tue 17 Nov 2026. Same points every visit, so next month's photos line up with these. 4 of 26 shown; all 26 are in your download.
P0117 Nov 2026 10:14 EAT · GPS ✓
P0517 Nov 2026 10:21 EAT · GPS ✓
P0917 Nov 2026 10:33 EAT · GPS ✓
P1117 Nov 2026 10:41 EAT · GPS ✓
| Electricity meter | Not installed yet (no meter box on site) |
| Water meter | Not seen (issue 4) |
| Water tank | Present; level not checked (we don't climb) |
| Wall height, front | About 2.9 m (tape from ground at P01) |
| Crack, tank stand | About 40 cm long (tape at P05) |
Nobody was on site, so there were no conversations. A neighbour at the next gate said, unprompted, that "they haven't worked for about two weeks." Told to us, not verified.
If you start Build Monitor within 14 days of this report, we take this Site Check off the first month. That would leave £96 (USD 126) for month one, and visits start from the plan start date.
We describe what we saw. We don't say whether to pay, guess causes or costs, or blame anyone. The decision is always yours.
Peter M., Nimda Site Check inspector (sample name)
Vetted by Nimda: ID, KRA PIN, police clearance, references, paid trial visit.
Independent: has no link to your contractor.
Nimda Site Check QC (sample)
Evidence complete · verdict matches issues · every photo captioned.
Questions? Reply on WhatsApp to the number on your invoice.
Arrival photo GPS was 18 m from the pin you sent. All 26 photos were taken within 70 m of each other between 10:12 and 10:58 EAT. Exact coordinates are kept off this report for your privacy.
Each file got a SHA-256 fingerprint when it was taken (ProofMode). If any file were edited later, its fingerprint would no longer match the list below.
| File | Taken (EAT) | SHA-256 fingerprint (sample values) |
|---|---|---|
| VID01 | 10:12:04 | 9f2c4e1a7b0d3c58e6f1a92b4d7c0e3f5a8b1c2d4e6f7089a1b2c3d4e5f60718 |
| P01 | 10:14:37 | 3b7e9a12c4d5f6e70819a2b3c4d5e6f7a8b9c0d1e2f3a4b5c6d7e8f9a0b1c2d3 |
| P05 | 10:21:10 | c81d0e2f3a4b5c6d7e8f90a1b2c3d4e5f6a7b8c9d0e1f2a3b4c5d6e7f8091a2b |
| P09 | 10:33:52 | 5e6f7a8b9c0d1e2f3a4b5c6d7e8f9a0b1c2d3e4f5a6b7c8d9e0f1a2b3c4d5e6f |
| P11 | 10:41:26 | a0b1c2d3e4f5a6b7c8d9e0f1a2b3c4d5e6f7a8b9c0d1e2f3a4b5c6d7e8f9a0b1 |
Full list of 27 files and the original photos and video are in your download link. No faces or number plates appear in this report.